D&G Contracting have recently completed the Drylining, Firestopping, and SFS packages at a new Head Quarters for ZX Lidar.

We were selected by Main Contractor Interclass PLC to carrying out the works following a collaborative tender process where we worked closely with Interclass to ensure specifications and quality materials were selected whilst also maintaining the packages budgets.

Our team were onsite for 8 months, starting with the SFS install using an EOS system with a Siniat Weather Defence external sheathing board, once this was completed, we were then focused on the internal partitions followed by Zentia suspended ceilings.

Following the successful commencement of SFS, our Firestopping Division were also selected by Interclass to carry out over 600nr firestopping penetrations throughout the project.

Client: Interclass

Services:
SFS – EOS
Ceilings – Zentia
Acoustic Baffles – Autex & Ecophon
Partitions – Siniat